The engineers were given a deadline of 4 hours to complete the task. But with a collective effort, the job was done way ahead of the given deadline.
The Ranchi Railway Division (RRD), on Sunday broke its own record by making an underpass in 2 hours and 40 minutes on the single line Karra-Govindpur route in Jharkhand.
Earlier, RRD had constructed an underpass between Lodhma and Karra in 3 hours and 15 minutes.
About 100 workers, three cranes, four JCB machines, three polken, and four tractors were used to construct this underpass. Indian railways had to pay about Rs 1.10 crore for its construction.
Image for representation
The engineers were given a deadline of 4 hours to complete the task. But with a collective effort, the job was done way ahead of the given deadline.
You can also read: 20 Incredible Facts About Indian Railways That You Probably Did Not Know
The construction started at 8.50 am on Sunday and ended at 11.30 am the same day. While the work was on, only Tapaswini Express was rescheduled by one hour.
The engineers said this underpass will benefit about 10,000 people from nearby areas. The RRD plans to make 49 more such underpasses in the coming months.
Like this story? Or have something to share? Write to us: contact@thebetterindia.com, or connect with us on Facebook and Twitter (@thebetterindia).
We bring stories straight from the heart of India, to inspire millions and create a wave of impact. Our positive movement is growing bigger everyday, and we would love for you to join it.
Please contribute whatever you can, every little penny helps our team in bringing you more stories that support dreams and spread hope.